Background
Starting point
The customer wanted a reliable, properly finished solution at the property in Bradwell Abbey, Milton Keynes. The starting point was large persistent leaks around a failing roof/gully area after previous roofers had attempted repairs. The priority was to correct the issue properly and leave a durable, professional finish.
Existing condition
Large persistent leaks around a failing roof/gully area after previous roofers had attempted repairs. The existing construction and surrounding details were assessed so the scope could focus on the areas genuinely requiring attention.
Challenges
"The main consideration was integrating the new work correctly with the existing property while maintaining weathering, finish and build quality. No unusual additional challenge is recorded for this historic project. Additional project context: QC had successfully used fleece-backed rubber on another section of the building the previous year. For this later gully, a flexible liquid-rubber system was selected because it could be worked more effectively into awkward commercial gutter details and around complex junctions."
Photography
Completed
Delivery
What we did
- Cut away the failing membrane, thoroughly cleaned and prepared the area and applied a liquid-rubber waterproofing system to specification
- This section was approximately 30 linear metres; a related front gully of approximately 70 linear metres had also been treated and resolved more than a dozen leaks.
Programme
Work stages
Inspection & preparation
Assess the existing substrate or prepared deck, remove failed material where required and clean the area thoroughly. QC focus: preparation, correct sequencing and quality of the inspection & preparation stage.
Repairs / build-up
Complete any structural, deck, DPM, insulation or upstand work required before waterproofing. QC focus: preparation, correct sequencing and quality of the repairs / build-up stage.
Waterproofing installation
Install the specified EPDM, single-ply or liquid-applied waterproofing system with careful detailing around edges, outlets and penetrations. QC focus: preparation, correct sequencing and quality of the waterproofing installation stage.
Trims & interfaces
Complete perimeter trims, wall details, fascias, gutters or adjoining roof interfaces. QC focus: preparation, correct sequencing and quality of the trims & interfaces stage.
Final inspection
Check continuity, laps/details and the finished appearance, then photograph and leave the area clean. QC focus: preparation, correct sequencing and quality of the final inspection stage.
Specification
Products & materials
Flexible liquid-rubber waterproofing system
- Specification
- Flexible liquid-applied membrane
Selected to form a continuous waterproof coating capable of accommodating normal thermal movement.
On site
Problems solved
Issue
The main consideration was integrating the new work correctly with the existing property while maintaining weathering, finish and build quality. No unusual additional challenge is recorded for this historic project.
How we fixed it
Quality Construction recommended a targeted, properly prepared installation rather than a temporary cosmetic repair. The agreed approach was to cut away the failing membrane, thoroughly cleaned and prepared the area and applied a liquid-rubber waterproofing system to specification. This section was approximately 30 linear metres; a related front gully of approximately 70 linear metres had also been treated and resolved more than a dozen leaks. with attention to preparation, detailing and long-term performance.
Outcome
The persistent leaks were resolved. The liquid-rubber system carried a 10-year guarantee, with 20 years available on a two-coat specification.
Standards
Planning, quality & handover
Quality control
Quality checks focused on preparation, alignment, weathering/detailing, fixings and the finished appearance relevant to this persistent roof leak & liquid rubber gully repairs – bradwell abbey, milton keynes. Photographs should be used to evidence visible and hidden-stage workmanship where available.
Project management
The works were organised around a planned sequence and completed over 2 days. Materials, access and individual work stages were coordinated so the project could progress efficiently with minimal unnecessary disruption.
Guarantees
Workmanship — 20 years
Outcome
The result
The persistent leaks were resolved. The liquid-rubber system carried a 10-year guarantee, with 20 years available on a two-coat specification.